|
Slippage in a three-quarter acre section of the earth-moving project
at Kinetic Park has been stabilized and is not expected to be a major
problem, according to Gerald McDonald, president of the Huntington Area
Development Council, the developers of the high tech park.
Motorists driving by the site began noticing slippage and settlement
of fill dirt on Sept. 9 in an area below W. Va. 10 adjacent to the re-located
Fourpole Creek.
During the placement of fill along Fourpole Creek, settlement
of the underlying native materials was encountered, according
to a statement from McDonald. About 40 feet of fill had been placed
in the area when cracks, fissures and settlement occurred in the fill
for a distance of approximately 100 feet from the top of the slope,
McDonald said.
The underlying soils have a high water content, making them liquid
under certain conditions, McDonald said. As a result, the original
soil underlying the fill moved laterally and heaved up.
Triad Engineers, the projects on-site engineering firm, noticed
the settlement on Sept. 9 and the following morning the contractor
was instructed to remove the top 10 feet of the fill in order to relieve
the pressure on the underlying materials. This work was completed and
the area has stabilized, McDonald said.
McDonald said the engineers believe too much fill was placed on the
underlying wet soil too quickly and did not allow the underlying
soils to adjust to the increased weight. Triad has recommended
slowing the fill rate which will squeeze the water out of the
soils slowly, thus allowing the water to dissipate and the materials
to consolidate.
Triad believes it will take three weeks for the soil underneath to stabilize.
Until that time fill in this problem area will be halted, McDonald said.
When it begins again, the fill will resume in five-foot increments with
a one-week waiting period between each fill.
This is a minor problem that was anticipated during project design,
McDonald said. The entire project is about 100 acres; the affected
area is approximately three-quarters of an acre.
Slightly less than half the earthmoving work has been completed at the
site. Kanawha Stone, the contractor, expects to complete the earthmoving
project by early December.
The original contract amount was for $7.2 million. The project budget
contains an 8 percent built-in contingency for unexpected problems,
McDonald said. That means the project could eventually cost about $570,000
more if more work than the contract calls for has to be done. To date,
two change orders have increased the original contract by $23,100.
|
|